Saturday, September 13, 2008

and it is Day 2 & Day 3...


DAY 2

This is what was done for yesterday. Concrete beams put up. Hmmm...it took them one day.
Weather has been cooperative last night.

DAY 3
Work stopped early today!!! A concrete gutter built. That's it?!!! I wanted more work to be done but the contractor said that is all that they are able to do. They have to wait for the gutter to dry. Aaarghhh...I want work to move faster....!!! Patience...patience. Now to hope the weather cooperate further. :o)
to be continued...